Schedule & Crew Plan
06 / 10
Committed dates, not estimates. Monday through Saturday, 7am to 4pm. No Sundays. No holidays.
Maple Ridge Townhomes • Edina, MN 55435 • Kickoff April 6, 2026
Phase
Wk 1
Wk 2
Wk 3
Wk 4
Wk 5
| Stage |
Duration per Unit |
What Changes |
| Tear-off | 1 day | Patio closed; windows on the active elevation covered |
| Housewrap & flashing | 1 day | Windows still covered; no entry interruption |
| Siding install | 2–3 days | Patio reopens; construction noise during work hours |
| Trim & cleanup | 1 day | Unit closed out; magnetic sweep before crew leaves |