Schedule & Crew Plan

06 / 10
Committed dates, not estimates. Monday through Saturday, 7am to 4pm. No Sundays. No holidays.
Maple Ridge Townhomes  •  Edina, MN 55435  •  Kickoff April 6, 2026
4
Installers On-Site
5
Calendar Weeks
3.5
Sq / Installer / Day
Project Timeline
Phase
Wk 1
Wk 2
Wk 3
Wk 4
Wk 5
Mobilize Materials
Building A 3 units
Building B 3 units
Punch & Closeout
What This Looks Like for Residents
Stage Duration per Unit What Changes
Tear-off1 dayPatio closed; windows on the active elevation covered
Housewrap & flashing1 dayWindows still covered; no entry interruption
Siding install2–3 daysPatio reopens; construction noise during work hours
Trim & cleanup1 dayUnit closed out; magnetic sweep before crew leaves